Question: 1 / 400

What is a key component of the SAFe Planning process?

The Daily Stand-up

The Program Increment (PI) Planning event

The Program Increment (PI) Planning event is a crucial element of the SAFe Planning process because it serves as the cornerstone event where teams come together to align on the vision, objectives, and plans for the upcoming Program Increment, typically a timeframe of 8-12 weeks. During this event, teams and stakeholders collaboratively plan the work by setting objectives, defining user stories, and identifying dependencies between teams. This alignment is essential for ensuring that all teams are working towards the same goals and understanding how their efforts contribute to the overall value delivery.

PI Planning also emphasizes face-to-face collaboration, which fosters trust and communication across teams, enhancing the ability to deliver value efficiently. It sets the stage for synchronization and coordinated delivery by providing a clear picture of what will be accomplished in the PI, which is fundamental to the iterative and incremental nature of SAFe.

The other components mentioned, like Daily Stand-ups, Sprint Reviews, and Retrospective Meetings, are important Agile practices but serve different purposes. Daily Stand-ups focus on team synchronization and immediate task progress, Sprint Reviews evaluate completed work at the end of a sprint, and Retrospective Meetings provide a forum for teams to reflect on process improvements. These elements are part of Agile practices but do not encompass the broader,

Get further explanation with Examzify DeepDiveBeta

The Sprint Review

The Retrospective Meeting

Next Question

Report this question

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy